Our patio is built!

Construction began around the middle of the summer holidays and finally, two weeks after the start of the school year, it’s open for the students.

It feels nice to be walking around the patio, knowing that you directly contributed to its final form.

1
3
6
1


Ultimately, the project cost the school 146842,26 PLN , so the cost estimate from our project (135,913.11 PLN) was quite close to reality, considering that we had no prior experience in estimating such amounts.

It’s just a pity that there weren’t enough funds left for a mural of the school’s patron – Jan Rzepa.